Welcome to PCI Blogs - selection of thoughts and tips shared by Project Controls community.
Refer to this list for definitions of essential Project controls / Cost Engineering / Earned Value management, terms submitted by Project Controls practitioners from around the world.
Welcome to PCI Templates - Selection of some practical Project Controls templates for the community.
Welcome to PCI Videos- Selection of some educational content to help you understand Project Controls
Welcome to PCI Paperback - Selection of some handpicked paperback literature for the community. This section will be replaced by spotify integrated books for easy reference




|
Hi
Is there any clear cut defination or guideline to define L-0,L-1,L2,L-3,L-4 schedule.According to me, Levels are the perception of the individual.
I have discussed the same with many but still i have received any conviencing reply.
Thanks
Nathan
|
|
|
|
Hi,
Common Schedule Level Descriptions
Level I: Milestone/Executive Master Summary schedule One‐pager, time scaled bar chart
Level II: Contract Master/Detailed Integrated schedule CPM to plan, implement & control overall project
Level III: Area Master/Contract schedules Subcontract/phased/element CPM schedules
Level IV: Control/detailed short term look‐ahead schedules Spreadsheets/Bar Chart field plans
Level V: Daily/Hourly Work schedules Field supervision planning & execution listings
Hope this helps
James
|
|
|