Welcome to PCI Blogs - selection of thoughts and tips shared by Project Controls community.
Refer to this list for definitions of essential Project controls / Cost Engineering / Earned Value management, terms submitted by Project Controls practitioners from around the world.
Welcome to PCI Templates - Selection of some practical Project Controls templates for the community.
Welcome to PCI Videos- Selection of some educational content to help you understand Project Controls
Welcome to PCI Paperback - Selection of some handpicked paperback literature for the community. This section will be replaced by spotify integrated books for easy reference
|
Hi
Some projects specially the industrial one the cost of procurement activities for the equipments are very high comparing to the cost of the construction activities, in the meantime, the man-hours of the procurement activities is very low comparing to the construction activities. When a share holder or an employer ask a question what is the overall percentage completion of the project
You may present the overall percentage completion of a project by one of the two scenarios:
1.Man-hour basis
But the problem that at some stages of the project The employer might make a comparison between what he have spent of the project budget and the overall percentage completion of the project and he will find out that he spent a considerable amount of the project budget but the project have not been progressed as expected.
2. Cost basis
If you use the cost basis to present the overall percentage there will be a big differences between the overall percentage on the documents and the actual status on site.
I solved this problem by presenting the two scenarios together and explaining the situation and why it look like that, but is there is a method that combine both together (man-hours and cost) or any other method.
Ryan
|
The following user(s) said Thank You: MUHAMMAD
|