Welcome to PCI Blogs - selection of thoughts and tips shared by Project Controls community.
Refer to this list for definitions of essential Project controls / Cost Engineering / Earned Value management, terms submitted by Project Controls practitioners from around the world.
Welcome to PCI Templates - Selection of some practical Project Controls templates for the community.
Welcome to PCI Videos- Selection of some educational content to help you understand Project Controls
Welcome to PCI Paperback - Selection of some handpicked paperback literature for the community. This section will be replaced by spotify integrated books for easy reference




|
Hello
What is the difference between Planning and Scheduling?
Olivia
|
|
|
|
Hi Olivia,
Planning determines what is to be delivered, how much it will cost, how it will be delivered and who will carry it out.
The planning represents the thinking phase of the project. Planning is strategic and tactical thinking about project execution.
Project Success is most often contingent upon an effective planning effort. planning precedes scheduling; without proper planning, scheduling is pointless and loses credibility.
Scheduling is a process of converting a general or outline plan for a project into a time-based schedule based on available resources and time constraints.
Schedule Development involves:
[li]Identify project activities[/li]
[li]Estimate activity duration[/li]
[li]Identifying and modelling relationships between activities[/li]
[li]Assign resources responsible for accomplishing activities[/li]
[li]Calculate activity start & finish dates[/li]
[li]Review & analyse schedule with stakeholders[/li]
Thanks
Matthew
|
|