Blogs


Welcome to Project Controls Institute, Australia blog.

Selection of thoughts and tips shared by Project Controls community.

test

Webinar: Virtual Open Day - Diploma of Project Controls

Continue reading
299 Hits
0 comments

Webinar : Effectively Integrate Project Controls with PMO, by Jagan Rao

Continue reading
84116 Hits
0 comments

Brief methodology for undertaking QSRA/QCRA

Lets first understand what is QRA and Monte Carlo?


Quantitative Risk Analysis (QRA) is a forecasting technique used to predict project cost and/or schedule outcomes, and to estimate an appropriate level of contingency. The QRA seeks to develop realistic project schedules and estimates for a genuine prediction on how the project may result. In the past, project contingency has often been set by means of an uplift (E.g. 10% on cost/time). This approach is rudimentary, often provides no justification on why a certain uplift is applied, and may result in an entirely inadequate risk contingency.

There is generally a finite number of occasions on which a project can baseline schedules/budgets; we can maximise our chances of success by utilising Monte Carlo Analysis (MC).

Monte Carlo is a mathematical technique utilising random sampling, within specified distributions to calculate the probability of explicit outcomes. The underlying principal of the method is rooted in the law of averages, and the law of large numbers; creating a mathematical prediction of how the process may eventuate.

MC uses input duration ranges, as opposed to single point estimates for activity durations, to offset the inherent uncertainty in estimating. For a holistic coverage of possible cost/schedule outcomes, Risk Events (with a defined probability of occurrence, as well as an impact duration range) can be assigned to activities within the programme and contribute to the analysis (effectively extending the linked activity by the nominated impact duration value, on any iteration in which it appears). The Risk Analysis model is simulated hundreds, or thousands of times, and on each iteration a value is randomly selected from within the defined duration range for each activity. The most widely used, and easily understandable, range distribution is a triangular distribution (often referred to as a 3-point estimate and provided as a minimum, most likely, and maximum). The MC simulation is entirely random, plotting the outputs of each iteration as it works to create several useful insights. MC analysis undertaken on a project schedule takes cognisance of logic uncertainty and calendars, creating forward and backward pass calculations for each relationship in the plan, ultimately providing confidence intervals based on the range of start/finish dates for each milestone/activity.

Cumulative distribution graphs (S-curves) can be created to inform probability distributions (from which we can extrapolate confidence percentiles e.g. P50/P90.) For example, a P50 project completion date of 1st December 2018 occurs within the 50th percentile of the output dates; this means that in 50% of all iterations the project finish date is on, or before, 1st December 2018.

A relatively risk adverse organisation may prefer QRA models to provide a P90 confidence of meeting the schedule/cost target, where the results of the analysis show that in only 10% of iterations this value is exceeded. Conversely, a more risk tolerant organisation may be willing to accept a confidence percentile south of P50.

A QRA can help to provide a realistic forecast, and illustrate the key driving factors within a plan, in addition to quantifying the schedule benefits of timely interventions. This information is conducive to effective, risk-based decision making.

QSRA

The purpose of a Quantitative Schedule Risk Analysis (QSRA) is to provide assurance that key milestones/objectives within a project schedule will be met.


A QSRA can help to provide a realistic forecast, and illustrate the key driving factors within a plan, in addition to quantifying the schedule benefits of timely interventions. This information is conducive to effective, risk-based decision making.


The following inputs are necessary prior to analysis:


· Reviewed and agreed deterministic plan, considered suitable for analysis. If the existing project plan file is not suitable, a plan of

· Duration ranges for each line in the plan – minimum (optimistic), most likely (deterministic) and maximum (pessimistic). Depending on the Distribution type selected, a 2-point range (Min to Max) may be sufficient.

· Project Risk Register. (Note – there may be a requirement to hold a separate risk review prior to the QSRA process to ensure sufficiently mature Quantitative risk information is held)

Workshop – A workshop may be held with project stakeholders to review the analysis inputs. Several component parts of the analysis can be established at the workshop, such as risk impact mapping and duration uncertainty.

Programme – The programme must be representative of the programme of works, and must follow planning guidelines (attached). The programme should be reviewed in the workshop, to the following end:

- A review of activity durations to assign Duration Uncertainty values to the deterministic programme durations. The project team must ensure that the Duration Uncertainty estimates do not account for the impact of Risk and should account for only the inherent uncertainty in estimating the activity duration. The project team must challenge uncertainties and risks to ensure that optimism bias has been accounted for, and that all values provided are met with sufficient challenge.

- A review of where bespoke risks are to be mapped to the programme – This is to be an appropriate activity (or activities) the risk impact may be assigned.

Risk Register – The project risk register, with associated probability and impact values – including any planned management actions, must be addressed as it is a component part of the analysis. Existing risks should be sense checked by QSRA workshop attendees, and any links/correlation between risks should be identified before being imported into the plan. All risks should have assigned probability of occurrence values (%) as well as a Time impact ranges. The likely impact of a risk may be expressed as a 3 -point estimate (minimum, most likely, maximum) or a 2-point estimate (minimum to maximum).

QCRA

The purpose of a Quantitative Cost Risk Analysis (QCRA) is to estimate an appropriate level of cost contingency to supplement the project estimate and provide confidence that the budgetary allowance will not be surpassed.

A fully quantified risk register is essential to undertake the Cost Risk Analysis. Each applicable cost risk must have assigned probability of occurrence values (%) as well as a Cost impact ranges. The likely impact of a risk may be expressed as a 3 -point estimate (minimum, most likely, maximum) or a 2-point estimate (minimum to maximum).

The Risk Register should contain justification of the impact ranges (a qualifying statement of how costs have been built up, specific to each risk). E.g. ‘Cost impact may be X hours allowance for SME input @ £Xp/h + additional equipment costs = £Xk + Contractor prelims at £X per day ’.

The Risk Register should be cross-referenced with the Cost Model to ensure the impact of specific Risks have not been included for already in the base estimate.

QCRA should be run on Target (post-mitigated) risk assessment. This relies on the stability of the assumption, that identified mitigations are successful and the results are as expected.

A Monte Carlo Analysis can be run on the Risk Register inputs; resulting in the conception of output values specific to the project (as confidence percentiles). Specialist software (E.g @Risk, Primavera Risk Analysis etc. must be used to undertake the anlaysis).

Risks that are >70% of occurrence at Target assessment, should be transferred into the base estimate (or via contractual transfer depending on the project phase) or eliminated by terminating the linked activity/activities.

Cumulative distribution graphs (S-curves) can be created to inform probability distributions (from which we can extrapolate confidence percentiles e.g. P50/P90.)

If you like to know more about Project Risk Analysis or require any support, please contact us at info@Projcon-Advisory.com

Continue reading
7342 Hits
0 comments

Webinar: Governance and Risk Management for Complex Portfolios, Programs and Projects by Laurie Bowman

Continue reading
97871 Hits
0 comments

Webinar:

Continue reading
98152 Hits
0 comments

Test

[embed=videolink]{"video":"https://projectcontrolsinstitute.com/images/Auditing.mp4","width":"400","height":"225"}[/embed]

Continue reading
305 Hits
0 comments

Project Controls Auditing Webinar by Dr. Sean Regan

Tags:
15
Continue reading
102327 Hits
0 comments

The future of Cost Engineering Webinar by Dr. Alexia Nalewaik

Continue reading
24361 Hits
0 comments

The future of Cost Engineering and Project Controls by Dr. Alexia Nalewaik

 

Continue reading
295 Hits
0 comments

Test

https://vimeo.com/255910598

Continue reading
300 Hits
0 comments

Webinar: "The future of Cost Engineering and Project Controls" by Dr. Alexia Nalewaik

https://vimeo.com/255910598 

Continue reading
275 Hits
0 comments

Test Video

Dfsadfsdfdsfsd[embed=videolink]{"video":"https://www.youtube.com/watch?v=RbNox4BJwl0","width":"400","height":"225"}[/embed]

Continue reading
203 Hits
0 comments

Project Controls Trailblazer Apprenticeship – Path forward

In this post, We are attempting to offer an overview on upcoming Project Controls Trailblazer Apprenticeship based on knowledge which comes from our engagement in the development of this standard. 

The Project Controls Technician Apprenticeship (Level 3) that is part of the Government’s Trailblazer programme that aims to establish new standards for apprenticeships and is committed to reaching three million apprenticeship starts in England by 2020. has been developed by an employer-led working group consisting of Project Control leaders from 40 organisations that deliver complex projects across engineering, energy, infrastructure, construction and manufacturing sectors. Professional bodies such as ACostE, APM, IRM and CICES have also contributed to the development together with training providers and academia

The standard and assessment plan are ready to be delivered and used and have been fully approved by the Minister of State for Skills at the Department of Education, giving the green light for the launch of the apprenticeship in Q3 2017. A funding band (core government contribution which is currently capped at £21k per apprentice has been assigned to the standard.

In beginning to promote the apprenticeship, we have found that employers have a positive approach to the Project Controls Technician apprenticeship but are not sure who to engage with to get started, how to achieve a return on investment against the new apprenticeship levy and how best to establish Project Control apprenticeships and use the flexibility in the way the programme can be configured to meet their requirements for a viable programme that at the same time satisfies the mandatory criteria required by government.

Project Controls Institute being an approved training provider (via our parent org) for this Apprenticeship has created a dedicated KB offering options to guide employers in the right direction to provide a sure start for training your Project Controls apprentices. Based on our professional knowledge, we have also devised the unique delivery approach to offer this training to our clients which can be seen on our website.

Finally, we will be offering further insight on this topic at Project Controls Expo in Masterclass, supported by Employer, ECITB and possibly some government representation (SFA/DoE). If you any questions in the meantime, feel free to contact us at info@ProjectControlsInstitute.com

Tags:
17
Continue reading
27403 Hits
0 comments

Rolling Wave Planning

Continue reading
17045 Hits
0 comments

Concept of Control Accounts and Work Packages

Continue reading
19594 Hits
0 comments

What is Undistributed Budget and Distributed Budget

Continue reading
16745 Hits
0 comments

Planning & Scheduling rules/principles

 

Let us first understand the terms i.e., planning & scheduling:

Planning is control of time on a project by:

·         Project Plans which optimise expenditure of time, recognise cost implications and reflect the contractual obligations for the design, procurement, construction and commissioning of plant facilities.

·         Regular updates of all project activities and their inter relationships.

·         Early indication of deviations from the approved project programme so that action can be taken to minimise their effect.

It is to be noted that key elements of plans are Scope of work and Method of execution including WBS.   

With regards to Scheduling, it is a determination of timing of events in the Project i.e., When tasks will be performed and its a reflection of plan. Here are main features of scheduling :

·         Provides comparison of actual progress against plan

·         Identify deviations from plan (problem areas)

·         Enables early corrective actions and adjustments to plan

In other words, scheduling is the science of using mathematical calculations and logic to predict when and where work is to be carried out in an efficient and time-effective sequence.

Here are some rules to minimise the chances of your plan to get failed and ensure project completes before or on time.

 

Ø   Most importantly, Project Planning & Scheduling must involve decisions concerning :

·         the overall strategy of how the work process is to be broken down for control;

·         how the control is to be managed;

·         what methods are to be used for design, procurement & construction;

·         the strategy for subcontracting and procurement;

·         the interface between the various participants;

·         the zones of operation and their interface;

·         maximising efficiency of the project strategy with respect to cost and time;

·         risk and opportunity management.

Ø   In the process of converting the plan into a schedule  the scheduler should determine:

·         the duration of the activities;

·         the party who will perform the activities;

·         the resources to be applied to the activities; and

·         the method of sequencing of one, or more activities in relation to other activities.

Ø   Depending upon the density of the schedule, the purpose for which it is to be used and the information available, an activity duration must be derived from following only. Any assumptions must be documented in case needs to be validated in future.

·         experience

·         industry standards

·         benchmarking

·         comparison with other projects

·         calculation from resources

·         specification.

Ø   The schedule must illustrate a realistic and practical project plan showing how the project is intended to be, in a form that is sufficiently accurate for its identified density.

Ø   Schedule must be capable of identifying the following:

·         the longest path to completion;

·         the longest path to intermediate key dates, or sectional completion dates;

·         logic and activities, which are critical from those, which are not critical to one, or more completion dates;

·         total float on each path;

·         free float on each activity, on each path;

Ø   The strategy for schedule review must take account of the development of the schedule as better information becomes available and, as the project proceeds, the increasing density of the schedule as it develops from initiation through the work on site to commissioning the completed project.

Ø   When change is imposed, scheduler must be able to identify it contemporaneously, the effect of delaying and disrupting causal events on the planned sequence and to advise team members on the likely effect of possible recovery strategies.

Ø   Risk is inevitable part of any program however if dealt well, can be brought under control. Contingency period to deal with risks should be designed to be identified separately for both the employers and the contractors risks and for those risks which are related to:

·         an activity, or chain of activities

·         a contractor, subcontractor, supplier, or other resource

·         an access, or egress date, or date of possession, or relinquishment of possession

·         the works, any defined section, and any part of the works.

Ø   For Schedule reporting , it is impracticable to use the whole of the schedule at any one time in its detail. For effective reporting it should be summarised to different degrees of summarisation for differing purposes. Most project scheduling software packages facilitate this hierarchical structuring by virtue of a summarisation, or roll-up facility.

Some basic tips:

  • Do not use Mandatory Constrained dates. If a constraint has been used, then "Start on or After" can be opted. Keep use constraints as minimal as possible.
  • Adopt Finish to Start logic as much as possible. Avoid SF links completely.
  • No "Dangles" at all in schedule. LOE tasks could be an exception here.
  • Avoid use of lags, especially long duration lags
  • Keep Level 3 activities to similar levels of detail whenever possible
  • Roll-ups from Level 3 to Level 2 must be "many to one" with no splitting of level 3 activities into individual level 2's
  • Status activities only after confirming its reliability & source
  • Make your activity ID's intelligent to identify where it belongs to.
  • WBS development is must before the creation of schedule
  • Avoid changing RD just to keep the activity out of critical path
  • Identify Key Events and Drop Dead Times before developing the plan
  • Schedules needs not to be way too detailed.
  • Be realistic irrespective of pressure from Client, Project Managers and Engineering/Construction leads.
  • Avoid "tweaking" of the logic to "make it fit."
  • Activities must be linear and sequential (Finish-to-Start), instead of being overlapped, i.e., successor starts before the predecessor - a version of "fast-tracking" at the molecular level.
  • Planning procedure should encompass familiarisation, outline plan, strategic plan and detailed plan along with planning method statement
  • Do not deceive (to mislead by a false appearance or statement). Don't mislead the schedule by false appearance
  • Get buy-in from the responsible owners of the plan. In absence of this, plan is no more than a worthless piece of paper.
  • Ensure the calendars are set before developing the plan to includes the holidays and working hours restrictions, if any.
  • Activity codes should identify the various attributes of the schedule as fields, the values of which will facilitate organisational changes, and facilitate filtering of important parts of the schedule.
  • Schedule review must check for buildability, content, integrity, constraints, open end tasks, long lags, negative lags, ladders and critical paths to name a few.

Summary:

Don't twist the plan, contort the plan, reduce the plan, expand the plan, modify the plan, distort the plan, adjust the plan, change the plan.. Instead, follow the plan..

Continue reading
418 Hits
0 comments

Process of establishing Performance Measurement Baseline

Continue reading
18174 Hits
0 comments

New Approaches to Level Scheduling

While there are differing views on the criteria that apply to summary- and detailed-level scheduling, it is generally understood that a coordinated approach is best. For example, Jelen's position is that there is no universal agreement on the number of schedule levels or their format, while others take a progression elaboration approach to developing coordinating schedules across various levels of a project.
Some methods suggest using more details, targets and objectives at each level, while others have traditionally not done so in many lower-level schedules. For example, level 2 schedule considerations vary widely, from including subdivided components, details or intents to including little to no higher-level details, summaries or intents.
 
Recent theories take a different approach to traditional level scheduling, especially regarding the details and information included in each level.
 
AACE International's Recommended Practice No. 37 (RP 37), Chartered Institute of Building (CIOB Guide) and the Guide to the Forensic Scheduling Body of Knowledge Part I (FSBOK Guide) each bring new ideas into the project planning and scheduling field. But the main concept of establishing a common detailed framework for a project is universal.
 
Developing a common work schedule framework from the onset allows for easier level schedule development as a project progresses. Of course, details will continue to be added to each level as activities are confirmed and processes are firmed-up.
 
By using a combination of RP 37 and the CIOB Guide suggestions, you can implement a progressive elaboration approach. This approach is based on the idea that it's impractical to plan a working schedule (with all of its details) at the onset on a project, since the schedule's density will increase as more information and details become available and are confirmed.
Additionally, the FSBOK Guide introduces a multi-level schedule hierarchy. This helps ensure logical summary-level and detailed-level scheduling for mega- and major contracts through the creation of a foundation schedule. This five-level approach divides each level's criteria into two categories: general intent and format, and scheduling objective. With this subdivision of criteria, each level is able to include all of the general details and information about the project and keep the team on the same page.
 
FSBOK's multi-level hierarchy divides the scheduling into five levels:
  • Level 1: Graphical snapshot of driving summary activities and logic for executive and senior managers.
  • Level 2: Establish the driving critical path and near-critical path to contract, and key milestones for senior managers, including the project manager.
  • Level 3: Detail needed for construction management, staging deliveries and project control for construction manager and scheduling staff.
  • Level 4: Working schedule that supports Level 3 sequences for area supervision.
  • Level 5: Look-ahead schedule for crew foremen and supervision.
Although all of the new approaches agree that a common framework should be developed, they disagree on a method for addressing schedule density or granularity through the progression of the project. CIOB advocates increasing density of downstream activities, whereas FSBOK promotes holding to a uniform schedule granularity. Each approach has its advantages, and one may work better for certain projects and schedules than another, so it's wise to be flexible and use alternative methods as needed.
 
Regardless of the approach taken, it's important to keep all levels on the same page, making sure they are connecting with the overall schedule. To that end, the new approaches suggest using a coding structure to ensure horizontal and vertical integration throughout the project.
Approaches to project scheduling and planning continue to evolve and change, and it's helpful to incorporate new ideas into your planning. But it's also critical to remember that while each project and project team works differently, it's vital to keep everyone on the same track through the duration of the project

 

 
Tags:
22
Continue reading
10264 Hits
0 comments

Discrete Effort-Start and End Method

Continue reading
8847 Hits
0 comments

Categories

Search

Australian Open Learning Pty Ltd t/a Project Controls Institute, Australia | RTO CODE :45806